Correct Answer - Option 4 : 18
Given:
To complete a work in the first case:
Number of workers worked = 12
Number of hours per day = 6 hours
Number of days taken = 16 days
To complete a work in the second case:
Number of workers worked = 8
Number of hours per day = 8 hours
Concept used:
M1D1H1 = M2D2H2
M → Number of men, D → Day and H → Hours
Calculations:
12 × 6 × 16 = 8 × D2 × 8 (∵ Here work done w1 = w2)
⇒ D2 = 18 days
∴ The required number of workers to complete work is 18