Correct Answer - Option 1 : 16
Given:
24 men complete a work in 16 days.
32 women complete work in 24 days.
Formula Used:.
M1.D1.T1.E1W1.C1=M2.D2.T2.E2W2. M1.D1.T1.E1W1.C1=M2.D2.T2.E2W2. Where,
\(\frac{{M1.D1.T1.E1}}{{W1.C1}} = \;\frac{{M2.D2.T2.E2}}{{W2.C2}}\)
M is the number of working men
D is the total number of days
T is total hours of working days
E is the efficiency of working men
W is total work
C is the consumption of working men
Calculation:
Now by using the formula,
24 men × 16 = 32 women × 24
⇒ m = 2w
m = 2 and w = 1 ---- (efficiency)
Total work,
24 men × 16
⇒ 24 × 2 × 16
⇒ 768 units
Now 16 men and 8 women worked for 12 days,
⇒ {16(2) + 8(1)} × 12
⇒ 40 × 12
⇒ 480 units completed by them.
Remaining work,
⇒ 768 – 480
⇒ 288 units
This unit needs to be completed in 4 days,
Now using the formula,
Let the working men be x
{x(2) + 8(1)} × 4 = 288
⇒ (2x + 8) = 72
⇒ 2x = 64
⇒ x = 32
32 men required to complete the remaining work in 4 days.
The increased number of men are 32 – 16 = 16
∴ The number of men required more is 16.