If a man can do 210 units of work in 7days. Find the number of days taken by him to complete the 570 units work.
1. 18 days
2. 19 days
3. 21 days
4. 29 days

1 Answer

0 votes
by (30.0k points)
selected by
 
Best answer
Correct Answer - Option 2 : 19 days

Given:

210 units of work completed in 7 days

Calculation:

As, 210 units of work is completed in 7 days.

1 unit of work is done in (7 ÷ 210) days

∴ 570 units of work is done in = (7 ÷ 210) × 570

\( {570 \ \over 30}\)

= 19 days

∴ The number of days taken by man to complete 570 units of work is 19 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.