A is half as efficient as B, B is twice as efficient as C. If B can do the work in 25 days, find in how many days the whole work will be completed if they work together. 


1. 10 days
2. 12.5 days 
3. 15 days 
4. 20 days 

1 Answer

0 votes
by (30.0k points)
selected by
 
Best answer
Correct Answer - Option 2 : 12.5 days 

Given :

A is half as efficient as B, B is twice as efficient as C and B can do the work in 25 days.

Concept used :

work efficiency is inversely proportional to the time taken to complete the work. 

Calculations :

Let the work efficiency of A, B and C be A, B and C . 

A = B/2 

⇒ A ∶ B = 1 ∶ 2 

B = 2C

⇒ B ∶ C = 2 ∶ 1 

So, 

⇒ A ∶ B ∶ C = 1 ∶ 2 ∶ 1 

Ratio of time for A, B and C = 1 ∶ 1/2 ∶ 1 

⇒ 2 ∶ 1 ∶ 2 

So, the time taken by A, B and C will be 50 days, 25 days and 50 days respectively.

⇒ (1/t) = (1/50) + (1/25) + (1/50)     (where t is the time when all work together to finish the work)

⇒ 1/t = 4/50 

⇒ t = 12.5 days 

∴ Option 2 will be the correct answer.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.