50 people can complete a piece of work in 30 days. If half workers left after completion of one-fifth of work, find the time taken in completing the work completely.


1. 50 days
2. 35 days
3. 54 days
4. 20 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 3 : 54 days

Given:

50 people can complete a piece of work in 30 days.

Half workers left after completion of one-fifth of work.

Concepts used:

Time = Work/Efficiency

Total Work = Number of days × number of people

Calculation:

Total Work done by 50 people in 30 days = 50 × 30 = 1500 unit

(1/5)th of work completed by 50 people = 1500 × 1/5 = 300 unit

⇒ Number of days taken to complete (1/5)th of work  = 300/50 ⇒ 6 days

Remaining work = 1500 - 300 = 1200 unit

Number of workers left = 50/2 = 25 workers

Remaining workers = 50 - 25 = 25 

Number of days taken by remaining workers to complete remaining work =  1200/25 ⇒ 48 days

⇒ Total number of days worked = 48 + 6 = 54 days

∴ Total work gets completed in 54 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.