Critical Path is always
1. the longest path
2. the shortest path
3. the most profitable path
4. the fastest path

1 Answer

0 votes
by (113k points)
selected by
 
Best answer
Correct Answer - Option 1 : the longest path

Concept:

  • Critical path is the longest path time-wise which can be determined from forward path method only.
  • The critical path is the longest path through the network and time along this path gives the project duration. Critical path joins those activities which are critical.
  • Critical path can be easily determined with the help of total float calculations. The activities on the critical path are those activities that have total float equal to zero.
  • The activities that control the project duration are the ones that have zero total floats and form a continuous chain or path starting at the first node and ending with the last node.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.