A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken it have taken B to do the work by himself?
1. 1.5
2. 1.8
3. 2.0
4. 2.2

1 Answer

0 votes
by (113k points)
selected by
 
Best answer
Correct Answer - Option 3 : 2.0

Suppose, A can complete the task in = x days,

B can complete the task in = y days

According to the question,

1/x + 1/y = 1/1.2

⇒ x + y = xy/1.2      ----(i)

A completes half the job in = x/2 days and B completes half the job in = y/2 days

⇒ x/2 + y/2 = 2.5

⇒ x + y = 5      ----(ii)

From (i) and (ii), we get,

xy/1.2 = 5

⇒ xy = 6

⇒ x = 6/y       ----(iii)

From (ii) and (iii) we get,

6/y + y = 5

⇒ 6 + y2 = 5y

⇒ y2 – 3y – 2y + 6 = 0

⇒ y(y – 3) – 2(y – 3) = 0

⇒ (y – 3) (y – 2) = 0

⇒ y = 3 or 2

For y = 3, x = 6/3 = 2

For y = 2, x = 6/2 = 3

∵ B is more efficient than A

∴ B take less days than A

∴ B would take 2 days to complete the task

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.