Correct Answer - Option 2 : 54
Given:
A can complete the task alone = 9 days
B can complete the task alone = 13.5 days
A, B, and C complete the task together = 4.5 days
C and D together can complete the task = 18 days
Concept used:
Total work = LCM
Formula used:
Efficiency = (Total work)/(Total time)
Calculations:
Let Total work be LCM of (9, 13.5, 4.5, 18) = 54 units
Person |
Days |
Total work |
Efficiency |
A |
9 days |
54 |
6 |
B |
(27/2) days |
54 |
4 |
A + B + C |
9/2 days |
54 |
12 |
C + D |
18 days |
54 |
3 |
⇒ Efficiency of A = 54/9 = 6 units
⇒ Efficiency of B = 54/13.5 = 4 units
⇒ Efficiency of C = 12 – (6 + 4) = 2 units
⇒ Efficiency of D = 3 – 2 = 1 unit
D alone can complete the work in = 54/1 = 54 days