Time taken by X to finish a piece of work is twice the time taken Y and thrice the time is taken by Z. If all three of them work together, it takes them 4 days to complete the entire work. How many days Y alone take to complete the task?


1. 10 days
2. 12 days
3. 14 days
4. 16 days

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 2 : 12 days

Given:

Time taken by X to finish a piece of work is twice the time taken Y and thrice the time taken by Z

X, Y, and Z together takes = 4 days

Calculation:

Time taken by X = x days

Time taken by Y = x/2 days

Time Taken by Z = x/3 days

⇒ (1/x) + (2/x) + (3/x) = 1/4

⇒ 6/x = 1/4

⇒ x = 24

∴ Time taken by B = x/2

⇒ 24/2

⇒ 12 days

∴ Y alone takes 12 days. 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.