Devika completed the school project in 20 days. How many days will Aarav take to complete the same work if he is 25% more efficient than Devika?
1. 16 days
2. 12 days
3. 14 days
4. 18 days

1 Answer

0 votes
by (54.5k points)
selected by
 
Best answer
Correct Answer - Option 1 : 16 days

Given:

Devika completed the school project in = 20 days

Aarav is 25% more efficient than Devika.

Calculation:

Let the days taken by Aarav to complete the work be x

The ratio of time taken by Aarav and Devika = 125 : 100

⇒ 5 : 4

∴ 5 : 4 :: 20 : x

⇒ x = (4 × 20)/5

⇒ x = 16

∴ Aarav takes 16 days. 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.