A, B and C can complete the work in 2 days. If A alone can complete the work in 4 days and C alone can complete it in 6 days. How many days can B alone accomplish the task?
1. 1/12
2. 12
3. 3
4. 24

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 2 : 12

Given:

Work done by all in one day = A + B + C = 1/ 2 

Work done by A in one day = 1/4

Work done by C in one day = 1/6

Calculation:

Work done by B in one day = 1/2 - [1/4 + 1/6]

= 1/2 - 10/24

= (24 - 20) / 48

= 4/48

= 1/ 12

So, B takes 12 days to accomplish the task.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.