0 votes
873 views
in General by (113k points)
closed by
As per IS 456:2000, minimum period before striking form work for vertical surface of the columns
1. 1 days
2. 7 days
3. 14 days
4. 28 days

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 1 : 1 days

Explanation:

As per Clause 11.3.1 of IS:456-2000

Type of Formwork

Minimum Period Before Striking Formwork

Vertical formwork to columns, walls, beams.

16 - 24 h (1 Day)

Soffit formwork to slabs

3 days

Soffit formwork to beams

7 days

Props to slabs

a. Spanning up to 4.5 m

b. Spanning over 4.5 m

7 days

14 days

Props to beams and arches

a. Spanning up to 6 m

b. Spanning over 6 m

14 days

21 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.