Correct Answer - Option 3 : The project is time under run and cost overrun
Explanation:
∵ Contractor agreed to build 30 sheds in 90 days
means 1 shed complete in 3 days
Price of 1 shed is Rs. 10000
So, 8 Shed complete in 24 days while contractor take only 20 days means the project is time under run.
Price of 8 shed = 8 × 10000 = 80000, whlie contractor has finished 8 shed with an actual cost of Rs. 85000 means the project is cost overrun.