If 8 men working 5 hours a day complete a job in 12 days, then 15 men working 4 hours a day will finish the job in how many days? Assume that all men work at same efficiency.
1. 15 days
2. 42 days
3. 12 days
4. 8 days

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 4 : 8 days

Given:

 8 men working 5 hours a day complete a job in 12 days

Calculation:

⇒ M1D1T1 = M2D2T2

⇒ 8 × 12 × 5 = 15 × D2 × 4

⇒ D2 = 8

∴ The required result will be 8.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.