P, Q, and R take 1 day to complete a work. If P works alone, he finishes the work in 2 days and if Q works alone he finishes it in 3 days. How long will it take R to complete the work alone?
1. 3 days
2. 4 days
3. 6 days
4. 7 days

1 Answer

0 votes
by (113k points)
selected by
 
Best answer
Correct Answer - Option 3 : 6 days

Given

P, Q and R complete works in 1 day when work together.

Calculation

P completes work in 2 days.

Work done by P in 1 day = 1/2

Q completes work in 3 days.

Work done by Q in 1 day = 1/3

Let R completes work in x days

Work done by R in 1 day = 1/x

According to question

(1/2) + (1/3) + (1/x) = 1

(3 + 2)/6 + (1/x) = 1

(5/6) + (1/x) = 1

(1/x) = 1 - (5/6)

(1/x) = (1/6)

x = 6

R completes work in 6 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.