If 6 men can do a piece of work in 10 days. then 4 men will complete the same work in
1. 15 days
2. 20 days
3. 16 days
4. 14 days

1 Answer

0 votes
by (113k points)
selected by
 
Best answer
Correct Answer - Option 1 : 15 days

Given:

Time taken by 6 men to complete a piece of work = 10 days

Formula Used:

If a person takes x days to complete a work, part of the work completed by him in one day = 1/x

Calculation:

Time taken by 1 man = 6 × 10 = 60 days

∴ The time taken by 4 men to complete the work = 60/4 = 15 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.