0 votes
113 views
in Aptitude by (114k points)
closed by
Ram can complete a work in 60 days, Shyam can complete the same work in 45 days, find the number of days Ram worked if Shyam left after completing 70% of the work together with Ram. 
1. 24
2. 30
3. 36
4. 42

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 3 : 36

Given :

Ram can complete the work in 60 days 

Shyam can complete the work in 45 days 

Concept used :

Person's per day work = Total work/Number of days he took to finish work 

Calculations :

Total work = LCM of 60 and 45 

⇒ 180 units 

Ram's per day work = 180/60 = 3 units 

Shyam's per day work = 180/45 = 4 units 

Ram and Shyam per day work = 3 + 4 = 7 units 

70% of the work is completed together 

70% of the work = 70% of 180 units 

⇒ 126 units 

Time taken by Ram and Shyam to complete this work = 126/7 

⇒ 18 days 

Now remaining work is completed by Ram alone 

Remaining work = 180 - 126 = 54 units 

Number of days taken by Ram = 54/3 = 18 days 

Total number of days Ram worked = 18 + 18 

⇒ 36 days 

∴ Ram worked for a total of 36 days 

 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.