13 men working 7 hrs a day can make 280 bricks in 10 days, then in how many days 39 men can make 396 bricks working 3 hrs per day?


1. 17
2. 11
3. 10
4. 13

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 2 : 11

Given:

Time taken by 13 men to make 280 brick = 10 days working 7 hrs daily

Formula used:

M1D1T1/W1 = M2D2T2/W2

Calculation:

Let the number of days required = a

∴ (13 × 7 × 10)/280 = (39 × 3 × a)/396

⇒ a = 11 days

∴ In 11 days the work will be finished.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.