Correct Answer - Option 2 : 11
Given:
Time taken by 13 men to make 280 brick = 10 days working 7 hrs daily
Formula used:
M1D1T1/W1 = M2D2T2/W2
Calculation:
Let the number of days required = a
∴ (13 × 7 × 10)/280 = (39 × 3 × a)/396
⇒ a = 11 days
∴ In 11 days the work will be finished.