Use app×
Join Bloom Tuition
One on One Online Tuition
JEE MAIN 2025 Foundation Course
NEET 2025 Foundation Course
CLASS 12 FOUNDATION COURSE
CLASS 10 FOUNDATION COURSE
CLASS 9 FOUNDATION COURSE
CLASS 8 FOUNDATION COURSE
0 votes
100 views
in Aptitude by (114k points)
closed by
A is 10% more efficient than B and B is 20% more efficient than C. While working together they can finish the work in 12 days. Find in how many days B can finish the work?
1. 40 days
2. \(35\frac15\) days
3. 30 days
4. \(25\frac13\) days

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 2 : \(35\frac15\) days

Given:

The efficiency of A = 110% × B

The efficiency of B = 120% × C

Time taken by (A + B + C) to complete the work = 12 days

Concept:

Efficiency × Total days taken to complete work = Total work

Calculation:

Efficiency of A = 110% × B

⇒ A/B = 11/10    ------(1)

Efficiency of B = 120% × C

⇒ B/C = 12/10 = 6/5      ------(2)

From (1) and (2;

Ratio of Efficiency of A, B and C = 33 ∶ 30 ∶ 25

Efficiency of (A + B + C) = (33a + 30a + 25a) = 88a

⇒ Total work done by A, B, C = (88a) × 12 = 1056a units      ------(3)

No of days taken by B to complete the work

= [1056a]/30a = \(35\frac15\) days

∴ B will take \(35\frac15\) days to complete the task.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.