Correct Answer - Option 2 :
\(35\frac15\) days
Given:
The efficiency of A = 110% × B
The efficiency of B = 120% × C
Time taken by (A + B + C) to complete the work = 12 days
Concept:
Efficiency × Total days taken to complete work = Total work
Calculation:
Efficiency of A = 110% × B
⇒ A/B = 11/10 ------(1)
Efficiency of B = 120% × C
⇒ B/C = 12/10 = 6/5 ------(2)
From (1) and (2;
Ratio of Efficiency of A, B and C = 33 ∶ 30 ∶ 25
Efficiency of (A + B + C) = (33a + 30a + 25a) = 88a
⇒ Total work done by A, B, C = (88a) × 12 = 1056a units ------(3)
No of days taken by B to complete the work
= [1056a]/30a = \(35\frac15\) days
∴ B will take \(35\frac15\) days to complete the task.