A can complete a piece of work in 4 days while B alone can complete it in 7 days. If A starts working and left after 2 days, in how many days can B alone complete the remaining piece of work? 


1. 5 days
2. 4.5 days
3. 3 days
4. 3.5 days

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 4 : 3.5 days

Given:

A can complete a piece of work in 4 days.

B alone can complete it in 7 days.

A starts working and left after 2 days.

Concepts used:

1 day work done by individual = Work/time

Time = Work/Efficiency

Calculation:

1 day work done by individual = Work/time

⇒ 1 day work of A = 1/4

⇒ 2 days work of A = 2/4 = 1/2

Remaining work = 1 – (1/2) = 1/2

B alone can complete the work in 7 days.

⇒ Time taken by B to complete 1 work = 7 days

⇒ Time taken by B to complete 1/2 work = (1/2) × 7 days = 3.5 days

∴ B alone can complete remaining piece of work in 3.5 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.