84 views
in Aptitude by (115k points)
closed by

A can complete the work in 27 days. B can complete the work in 54 days. A started the work and left after 3 days. Remaining work completed by B. In what time work had completed?


1. 17
2. 51
3. 48
4. 32

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 2 : 51

Given:

A can complete the work in = 27 days

B can complete the work in = 54 days

Calculation:

⇒ One day work of A = 1/27 

⇒ One day work of B = 1/54

⇒ 3 days of the work of A = 3/27 = 1/9

⇒ Remaining work = 1 - 1/9 = 8/9

⇒ B will complete the remaining work = (8/9) × 54 = 48 days

⇒ Total work will be completed = 48 + 3 = 51 days

∴ The required result will be 51 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.