Correct Answer - Option 2 : 51
Given:
A can complete the work in = 27 days
B can complete the work in = 54 days
Calculation:
⇒ One day work of A = 1/27
⇒ One day work of B = 1/54
⇒ 3 days of the work of A = 3/27 = 1/9
⇒ Remaining work = 1 - 1/9 = 8/9
⇒ B will complete the remaining work = (8/9) × 54 = 48 days
⇒ Total work will be completed = 48 + 3 = 51 days
∴ The required result will be 51 days.