Which is the correct sequence of jobs in construction management?
1. Planning, Scheduling & Controlling
2. Planning, Controlling & Scheduling
3. Scheduling, Planning & Controlling
4. Controlling, Planning & Scheduling

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 1 : Planning, Scheduling & Controlling

Phases of Project management:

(1) Planning: Planning involve

(i) Defining the objective of the project.

(ii) Listing of jobs that have to be performed.

(iii) Determining gross requirements for materials, equipment and manpower and preparing estimates of costs and duration for various jobs.

(iv) To bring about the satisfactory completion of the project

(2) Scheduling: Scheduling is the allocation of resources such as time, material, space, equipment and human and technological effort.

It involves:

(i) Finalizing the planned functions mechanically.

(ii) Assigning starting and completion dates to each activity to proceed in a logical sequence and in a systematic manner.

(3) Controlling:

(i) Determination of deviations from the basic plan and their effects on the project.

(ii) Replanning and rescheduling of activities to compensate for the deviations which are called “Updating”

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.