Correct Answer - Option 4 : 198000
Explanation:
Total cost = Direct cost + Indirect cost
Total cost = 160000 + 20000 = 180000
According to the question, the markup applied is 10% of the bid price.
Mark up cost = 0.10 × 180000 = 18000
Quoted price = 180000 + 18000 = 198000
Indirect project Cost: Indirect project cost are those expenditures which cannot be clearly allocated to the individual activities of the project, but are assessed as a whole.
The indirect cost rises with an increase in duration.
Direct Project Cost: These include labour cost, material cost, equipment cost etc.
Direct cost decreases with an increase in duration.