0 votes
319 views
in General by (239k points)
closed by
For the construction of water bound macadam roads, the correct sequence of operation after spreading coarse aggregates is
1. Dry rolling, wet rolling, application of screening and application of filler
2. Dry rolling, application of filler wet rolling, and application of screening
3. Dry rolling, application of screening, wet rolling, and application of filler
4. Dry rolling, application of screening, application of filler and wet rolling

1 Answer

0 votes
by (237k points)
selected by
 
Best answer
Correct Answer - Option 3 : Dry rolling, application of screening, wet rolling, and application of filler

Explanation

Water bound macadam roads: 

In this method, the broken stones of the base course and surface course, if any, are bound by the stone dust in presence of moisture. 

The roads whose wearing course consist of clean crushed aggregates, mechanically interlocked by rolling and bound together with filler material and water and laid on a well compacted base course, is called water bound macadam road.

The Process of WBM is

1. Dry Rolling

2. Application of screenings

3. Sprinkling and grouting

4. Wet rolling

5. Application of binding material

6. Checking for surface unevenness and Rectification

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.