Correct Answer - Option 2 : 12 days
Given:
Suhani does 1/3rd of a job in 20 days
Remaining work done by Megha = (1 – 1/3)
⇒ (3 – 1)/3
⇒ 2/3rd in 10 days
Concept used:
If a person does a work in ‘n’ days, then one day work will be 1/n part of total work.
Total time taken for one work = number of days/part of the work
Calculation:
One work done by Suhani = 10 × 3/2
⇒ 15 days
Then one day work by Suhani = 1/15 part of total work
One work done by Megha = 20 × 3
⇒ 60 days
Then one day work by Megha = 1/60 part of total work
Now, the one day work by Suhani and Megha = one day work by Suhani + one day work by Megha
⇒ 1/15 + 1/60
⇒ (4 + 1)/60
⇒ 5/60
⇒ 1/12
Then one work done by both Suhani and Megha = 12 days
∴ The work done by both when work together in 12 days