Correct Answer - Option 1 : 45 days
Given:
5 men and 3 boys can do work in 40 days
6 men and 2 boys can do this work in 36 days
Calculation:
According to the question:
(5M + 3B) × 40 = (6M + 2B) × 36
⇒ 50M + 30B = 54M + 18B
⇒ 50M – 54M = 18B – 30B
⇒ 12B = 4M
⇒ 1M = 3B
Now, (5M + 3B) = 5 × 3B + 3B
⇒ 15B + 3B = 18B
Again,
(4M + 4B) = 4 × 3B + 4B
⇒ 12B + 4B = 16B
18 boys take time 40 days.
1 boys take time = (40 × 1) days
16 boys take time = (40 × 18)/16 = 45 days
∴ 4 men and 4 boys to complete work in 45 days.