Correct Answer - Option 1 : 20 : 18 : 15
Given:
Ratio of efficiency of A, B and C = 9 : 10 : 12
Time taken by them to finish the job working together = 3 days
Formula used:
Total work = work done rate × time
Calculations:
Let us assume, efficiencies of A, B and C are 9x, 10x and 12x respectively.
Working together, amount of work done by them/day = (9x + 10x + 12x) = 31x
Total work = 31x × 3 = 93x
If A works alone, time required to finish = 93x/9x = 31/3 days
If B works alone, time required to finish = 93x/10x = 93/10 days
If C works alone, time required to finish = 93x/12x = 93/12 days
Required ratio = 31/3 : 93/10 : 93/12 = 1/3 : 3/10 : 3/12 = 20 : 18 : 15