Which of the following quantities is NOT measured in square meter?
1. Damp proof course
2. Leaf of doors and windows in wood
3. RCC work for staircase
4. Painting on walls and underside of slab

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 3 : RCC work for staircase

Explanation:

Following are the item of work which is measured in different quantities shown in the tabular form.

Item of work

Quantities measured in

Earthwork

Cubic meter (m3)

Concrete in foundation

Cubic meter (m3)

Damp proof course (D.P.C)

Square meter (m2)

Masonary

Cubic meter (m3)

R.C.C and R.B work

Cubic meter (m3)

Plastering and pointing

Square meter (m2)

Door and window leaves or shutters

Square meter (m2)

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.