A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.


1. 8 days
2. 10 days
3. 6 days
4. 9 days

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 1 : 8 days

Given:

Time taken by A to complete the work = 12 days

Time taken by B to compete the work = 24 days

Formula used:

Efficiency = Total work/Time taken

Calculation:

LCM of 12 and 24 = 24 = Total work

Efficiency of A = 24/12 units/day

⇒ 2 units/day

Efficiency of B = 24/24 unit/day

⇒ 1 unit/day

Total efficiency of A and B = (2 + 1) units/day

⇒ 3 units/day

Required time = 24/3 days

⇒ 8 days

∴ The time taken by both A and B together to complete the work is 8 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.