Three people P, Q, R can do a piece of work in 18 days, 24 days, and 30 days respectively. if P works regularly and (Q + R) help him every third day. how long will it take for them to complete the work?
1. 12 days
2. \(12\frac12\) days
3. \(12\frac35\) days
4. 13 days
5. \(13\frac23\) days

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 3 : \(12\frac35\) days

GIVEN:

time taken by P to complete the work = 18 days 

time taken by Q to complete the work = 24 days

time taken by R to complete the work = 30 days

P is helped by Q and R every third day

EXPLANATION:

let the total work be 360(L.C.M of 18, 24, 30 )

P's work per day = 20

Q's work per day = 15

R's work per day = 12

work done in three days = 20 × 3 + (15 + 12) = 87

work done in 12 days = 87 × 4 = 348

remaining 12 work will be done by P in \(\frac{12}{20} = \frac35days\)

∴ total time = \(12\frac35days\)

 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.