The peak load on a power plant is 60 MW. The loads having maximum demands of 30 MW, 20 MW, 10 MW and 15 MW are connected to the power plant. Find the diversity factor.
1. 1.11
2. 0.9
3. 1.25
4. 0.8

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 3 : 1.25
Concept:

Diversity factor: The ratio of the sum of individual maximum demands to the maximum demand on the power station is known as a diversity factor.

\(Diversity\;factor = \frac{{Sum\;of\;individual\;maximum\;demands}}{{Maximum\;demand\;on\;power\;station}}\)

A power station supplies load to various types of consumers whose maximum demands generally do not occur at the same time. Therefore, maximum demand on the power station is always less than the sum of individual maximum demands of the consumer. Hence diversity factor is always greater than 1.

The knowledge of diversity factor is vital in determining the capacity of the plant equipment.

The greater the diversity factor, the lesser is the cost of generation of power. Because greater diversity factor means lesser maximum demand. Now, lower maximum demand means a lower capacity of the plant which reduces the cost of the plant.

Calculation:

Sum of maximum individual demand = 30 + 20 + 10 + 15 = 75 MW

Maximum demand of the station = 60 MW

Diversity factor \( = \frac{{75}}{{60}} = 1.25\)

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.