If 12 men complete one-fourth of a piece of work in 10 days, working 8 hours a day, in how many days 15 men complete full piece of work when they work 6 hours a day? 
1. 128/3 days
2. 40 days
3. 130/3 days
4. 70/3 days

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 1 : 128/3 days

Given:

12 men complete one-fourth of a piece of work in 10 days, working 8 hours a day.

Concept used:

M1 × D1 × H1/W1 = M2 × D2 × H2/W2 

Where,

M → Number of men,

D → Number of days,

H → Number of hours,

W → Work

Calculation:

M1 × D1 × H1/W1 = M2 × D2 × H2/W2 

⇒ 12 × 10 × 8/(1/4) = 15 × D2 × 6/1

⇒ D2 = (12 × 10 × 8 × 4)/(15 × 6)

⇒ D2 = 128/3 days

∴ 15 men would complete full piece of work in 128/3 days when they work 6 hours a day.  

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.