A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:
1. Annual repair cost estimate
2. Revised cost estimate
3. Approximate quantity method cost estimate
4. Supplementary estimate

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 4 : Supplementary estimate

Explanation:

Supplementary estimate

i) It is a detailed estimate of additional work and is prepared when additional works or changes are required to supplement the original works, during the execution of work.

ii) Then a fresh detailed estimate of additional works is prepared in addition to the original works.

iii) The abstract should show the amount of the original estimate and the total amount including the Supplementary amount, for which sanction is required.  

Revised estimate

It is a detailed estimate and is required to be prepared under any one of the following circumstances:

i) When the original sanctioned estimate is likely to exceed by more than 5 %.

ii) When the expenditure on work exceeds or likely to exceeds the amount of administrative sanctioned by more than 10 %.

iii) If there is a change of rate or quantity of materials.

iv) Major additions or alterations are introduced in the original work.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.