A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 15 days, A finished the remaining work. In how many days A alone can finish the job?
1. 40 days
2. 30 days
3. 35 days 
4. 45 days

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 4 : 45 days

Given:

No. of days required by A and B together = 30 days

Concept used:

Total work = No. of days × Efficiency of work

Calculation:

Let the whole work be 1.

⇒ (A + B) × 30 = 1

1 day efficiency of A and B together = 1/30

20 days work of A and B together = 20/30 = 2/3

Remaining work = 1 – 2/3 = 1/3

15 days work of A = 1/3

1 day work of A = 1/45

45 days work of A = 1

A alone can do the entire work in 45 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.