Correct Answer - Option 4 : 3.85 m
3
Concept:
Wet Qty. of concrete = Area × thickness
Dry vol. of concrete = 1.54 × Wet volume of concrete
No. of cement Bags = Cement Qty/0.035
Calculation:
Area = 100 sq.m
Floor thickness = 2.5 cm
Concrete grade = 1:2:4
Wet quantity of concrete = 100 × 0.025 = 2.5 m3
So, to produced 2.5 m3 of wet concrete, dry concrete required = 1.54 × 2.5 = 3.85 m3
Bulk density of cement = 1440 kg/m3
1 bag of cement = 50 kg
Cement bags required = Volume of cement × 1440/50