Correct Answer - Option 2 :
\(2\frac{6}{9}\) days
Given:
A completes 3/4th part in 9 days
Efficiency ratio of A, B, and C = 2 ∶ 3 ∶ 4
Concept used:
Time ratio = 1/Efficiency ratio
Total Time together to complete work = Work/1-Day work
Calculation:
Time to complete 3/4th part of work by A = 9 days
⇒ Time to complete work by A = 9 × 4/3
⇒ Time to complete work by A = 12 days
Efficiency ratio of A, B, and C = 2 ∶ 3 ∶ 4
Time ratio = 1/Efficiency ratio
Total time ratio by A, B, and C = 1/2 ∶ 1/3 ∶ 1/4
⇒ Required ratio = 6 ∶ 4 ∶ 3
So, the total time to complete a work by A, B, and C is 6x days, 4x days, and 3x days respectively.
Time to complete work by A = 12 days
⇒ 6x = 12 days
⇒ x = 2 days
Time to complete work by B = 4x
⇒ Time to complete work by B = 8 days
Time to complete work by C = 3x
⇒ Time to complete work by C = 6 days
One day work of A = 1/12
One day work of B = 1/8
One day work of C = 1/6
A, B, and C together complete 1-day work = 1-day work of A + 1-day work of B + 1-day work of C
⇒ Required 1-day work = 1/12 + 1/8 + 1/6
⇒ Required 1-day work = (2 + 3 + 4)/24
⇒ Required 1-day work = 9/24
Total Time together to complete work = Work/1-Day work
⇒ Total Time together to complete work = 1/(9/24)
⇒ Total Time together to complete work = 24/9 days
∴ Total Time together to complete work is \(2\frac{6}{9}\) days.