Correct Answer - Option 2 : B
Given:
M1 = 32 men
H1 = 6 hours
D1 = 10 days
H2 = 10 hours
D2 = 12 days
Here, M is the number of men, H is time in hours and D is the number of days.
Formula used:
M1 × D1 × H1 = M2 × D2 × H2
Calculation:
32 × 10 × 6 = M2 × 12 × 10
⇒ M2 = 1920/120
⇒ M2 = 16
∴ 16 Men are needed to finish the work in 12 days by working 10 hours per day.