32 men can work for 6 hours daily and can complete a work in 10 days. How many men are needed to finish this work in 12 days by working 10 hours per day?

A. 15

B. 16

C. 17

D. 18


1. C
2. B
3. A
4. D

1 Answer

0 votes
by (238k points)
selected by
 
Best answer
Correct Answer - Option 2 : B

Given:

M1 = 32 men

H1 = 6 hours

D1 = 10 days

H2 = 10 hours

D2 = 12 days

Here, M is the number of men, H is time in hours and D is the number of days.

Formula used:

M1 × D1 × H1 = M2 × D2 × H2 

Calculation:

32 × 10 × 6 = M2 × 12 × 10

⇒ M2 = 1920/120

⇒ M2 = 16

∴ 16 Men are needed to finish the work in 12 days by working 10 hours per day.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.