P and Q undertake to do a piece of work for Rs. 4848. P alone can do it in 12 days while Q alone can do it in 16 days. With the help of R, they finish work in 6 days. Then find the share of R?


1. Rs. 808
2. Rs. 612
3. Rs. 606
4. Rs. 202

1 Answer

0 votes
by (238k points)
selected by
 
Best answer
Correct Answer - Option 3 : Rs. 606

Given:

P can do work = 12 days

Q can do work = 16 days

P, Q, and R together work = 6 days

Concept used:

Total work = LCM

Divide the money according to the ratio of efficiency

Formula used:

Efficiency = Work/Time

Calculations:

Total work = LCM of 12, 16, 6 = 48

Person

Time

Total work

Efficiency

P

12 days

48

48/12 = 4

Q

16 days

48

48/16 = 3

P + Q + R

6 days

48

48/6 = 8

 

Then efficiency of R = 8 – 7 = 1

Efficiency of P ∶ Q ∶ R = 4 ∶ 3 ∶ 1

Share of R = (4848/8) × 1 = Rs. 606

Share of R is Rs.606 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.