A and B can complete a piece of work in 18 days and 45 days respectively, they start work together but B left after some time and A finish the remaining work in 4 days, After how many days from the start B did leave the work?


1. 12 days
2. 10 days
3. 9 days
4. 14 days
5. None of these

1 Answer

0 votes
by (238k points)
selected by
 
Best answer
Correct Answer - Option 2 : 10 days

Given:

A alone can complete work = 18 days

B alone can complete work = 45 days

A and B start working together but B left after some time and A finish the remaining work in 4 days

Concept:

Total work = Time × Efficiency

Calculation:

Work done by

Time taken

(in day)

Efficiency

A

18

90/18 = 5

B

45

90/45 = 2

Total work = L. C. M. = 90

 

Start work together but B left after some time and A finish the remaining work in 4 days

Last 4 days work done by A = 4 × 5 = 20 unit

Work for did together = 90 – 20 = 70 unit

Efficiency of A and B = 5 + 2 = 7 unit

Let, After x days from the start B did leave the work

Then, x = 70/7 = 10 days

∴ After 10 days from the start B did leave the work

 

 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.