Correct Answer - Option 3 : Work Breakdown Structure
Explanation:
Work Breakdown Structure: a) The Work Breakdown Structure (WBS) is developed to establish a common understanding of project scope.
b) It is a hierarchical description of the work that must be done to complete the deliverables of a project.
c) Each descending level in the WBS represents an increasingly detailed description of the project deliverables.