Load flow study is carried out for 
1. Fault calculation
2. Stability studies
3. System planning
4. Load frequency control

1 Answer

0 votes
by (121k points)
selected by
 
Best answer
Correct Answer - Option 3 : System planning

Load Flow Study:

  • The flow of electrical power in any interconnected electrical system is termed as Load Flow.
  • The Load Flow Study is conducted to calculate the voltages at the various buses. It is also used for the study of the short-circuit conditions or any interconnected power system.
  • The load flow study is essential for the operation of the power system under an operating condition, its improvement and future expansion.
  • Load flow study generally carried out for System planning.
  • The load flow study determining the best location, as well as the optimal capacity of the generating station, substation and the new lines.
  • In the load flow studies in power systems, three types of buses are identified. In each bus, two variables are known, and the other two are to be calculated.

Classification of bus bars:

Voltage magnitude = |V|

Voltage phase angle = δ

Active power = P

Reactive volt-amperes = Q

Bus Type

Known parameters

Unknown parameters

Load bus / PQ bus

P, Q

|V|, δ

Generator bus/ PV bus/

Voltage-controlled bus

P,|V|

Q, δ

Slack bus/Swing bus/Reference bus

|V|, δ

P, Q

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.