Correct Answer - Option 2 : 34(2/3) days
Given:
X and Y finish work together in 26 days.
X leaves after 10 days.
Y and Z finish the remaining work in 16 days.
The ratio of efficiency of X and Y = 3 ∶ 1
Concept used:
Work = Time × Efficiency
Calculation:
Total work done by X and Y = (1x + 3x) × 26 = 104x
Let the efficiency of Z be ‘z’.
Total work = (1x + 3x) × 10 + (1x + z) × 16
⇒ 104x = 40x + (1x + z) × 16
⇒ 1x + z = 4x
Or, efficiency of Z = 3x
Time is taken by Z to finish the work alone = 104x/3x = 34(2/3) days.
∴ Z will take 34(2/3) days to finish the work.