Correct Answer - Option 3 : 4/3 days
Given:
Time to complete work by A = 10/3 days
Time to complete work by B and C together = 20/9 days
Efficiency of B = 125% efficient than C
Concept used:
One day work = 1/Total days to complete work
Total number of days to complete work = Work/One day work
Calculation:
Time to complete work by A = 10/3 days
One day work of A = 1/(10/3)
⇒ One day work of A = 3/10
Time to complete work by B and C together = 20/9 days
⇒ One day work of B and C together = 1/(20/9)
⇒ One day work of B and C together = 9/20
One day work to complete A, B, and C together = One day work of A + One day work of B and C together
⇒ Required one day work = 3/10 + 9/20
⇒ Required one day work = (6 + 9)/20
⇒ Required one day work = 15/20
⇒ Required one day work = 3/4
Total number of days to complete work = Work/One day work
⇒ Required total days = 1/(3/4)
⇒ Required total days = 4/3 days
∴ 4/3 day to complete same work by A, B, and C.