A portion of the total float within which an activity can be delayed for start without affecting the floats of preceding activities is called 

(a) Safety float 

(b) Free float 

(c) Independent float 

(d) Interfering float

Please log in or register to answer this question.

1 Answer

+1 vote
by (38.1k points)

(c) Independent float 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.