A contract on construction job specifies a penalty for delay of completion beyond a certain limit as follows: Rs.200 for first day, Rs. 250 for second day, Rs.300 for third day, etc. If the contractor pays Rs.27,750 as penalty, find the numbers of days for which the construction work is delayed. 

1 Answer

+1 vote
by (87.4k points)
selected by
 
Best answer

Here, a = 200, d = 50, Sn = 27750 

Comparing it with ax2 + bx + c = 0, we get 

But n  -37 as number of days cannot be negative. 

∴ Number of days are 30.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.