Different expenditures incurred on the construction of a building were shown by a pie diagram. The expenditure rs 45,000 on cement was shown by a sector of central angle of `75^@` . What was the total expenditure of the construction ?
A. 2,16,000
B. 3,60,000
C. 4,50,000
D. 7,50,000

Please log in or register to answer this question.

1 Answer

0 votes
by (123k points)
Correct Answer - A

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.