The following information is available for two sections of a factory. Obtain the combined standard deviation of the production time.

Section A Section B
No. of workers 10 40
Mean production time per unit (minute) 25 20
Variance 16 25

1 Answer

+1 vote
by (73.6k points)
selected by
 
Best answer

Section A:

n1 = No. of workers =10

1 = Average production time per unit = 25

s11 = Variance =16

Section B :

n2 = No. of workers = 40

2 = Average production time per unit = 20

s22 = Variance = 25

Combine mean of production time per unit of Section A and Section B:

Combined standard deviation of production time per unit of Section A and Section B :

d1 = x̄1 – x̄c = 25 – 21 = 4

∴ d12 = 16

d2 = x̄2 – x̄c = 20 – 21 = -1

∴d21 = 1

s1 = 4 ∴ s12 = 16: s2 = 5 ∴ s22 = 25

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.