Correct option is (b) 12 days
X does the work in 8 days.
∴ In 1 day X does \(\frac 18\) work,
Y does the work in 12 days.
∴ In 1 day Y does \(\frac 1{12}\) work and
Z does the work in 16 days.
∴ In 1 day Z does \(\frac 1{16}\) work.
So, In 2 days, X does 2 × \(\frac 18\) work = \(\frac 14\) work,
Now the work left after Y leaves = 25% work = \(\frac 14\) work
This is done by Z in \(\frac 14\) × 16 days = 4 days.
So Y's share of work = \(\left(1 - \frac 14 - \frac 14\right)\) work = \(\frac 12\) work
This work he will do in \(\frac 12\) × 12 days = 6 days.
∴ The total number of days required to finish the work
= (2 + 6 + 4) days
= 12 days.