Correct option (a) 16/3 days
Explanation:
Given
⇒ 4m +6w → 8 days
⇒ 32m + 48w → 1 day……(i)
⇒ 2m + 9w → 8 days
⇒16m + 72w → 1 day3………….(ii)
⇒ From equation (i) = (ii)
⇒ 32m + 48w = 16m +72w
⇒ 32m – 16m = 72w – 48w
⇒ 2m = 3w
⇒Here, it is given that a group of 4 m +6 women can do the work in 8 days, converting the whole equation into women.
⇒ 4m + 6w → 8 days
⇒ (2 ×2m)+6w → 8 days
⇒ (2×3w)+6w → 8 days
⇒ 6w + 6w → 8days
⇒ 12w → 8 days
i.e. 12 women can do the work in 8 days
⇒ Then a group of 18 women can do the work