7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days?

(a) 28

(b) 21

(c) 14

(d) 7

1 Answer

+1 vote
by (71.0k points)
selected by
 
Best answer

Correct option (c) 14

Explanation:

(n is additional no of men required)

21 = 7 + n

n = 14 men

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.